Request For Quotations

Channel Improvement in the Alta Vista Business Park, Lots 11 & 12

The RFQ has also been sent to the email address you provided.

Reminder

Important Dates

Pre-Bid Site Walk - Friday, April 24, 2026 @ 10:00 AM

Questions Deadline - April 30, 2026 @ 5:00 PM

Quote Submission Deadline  - Monday, May 12, 2026 @ 4:00 PM

Award Notification (est.) - Week of May 18, 2026

Anticipated Construction Start - June 1, 2026

Submission Instructions

Quotations must be received no later than Monday, May 12, 2026 at 4:00 PM.

Late submissions will not be accepted. Faxed or verbal quotations will not be accepted.
Submit as a sealed envelope or electronic PDF clearly labeled:

"QUOTATION – Channel Improvement RFQ No. 2026-1813.03 – DO NOT OPEN BEFORE May 12, 2026 @ 4:00 PM"

Submit to:
Mon Valley Alliance
Jamie Colecchi, Chief Executive Officer
235 West Main Street
Monongahela, PA 15063
Email (electronic submissions): jcolecchi@monvalleyalliance.org


All quotations will be opened and recorded after the deadline.

Results will be shared with all participating bidders upon request.

Point of Contact

All inquiries must be submitted in writing.

Verbal inquiries will not be accepted and verbal answers are not binding.

Mon Valley Alliance
Jamie Colecchi, Chief Executive Officer
235 West Main Street
Monongahela, PA 15063
Email (electronic submissions): jcolecchi@monvalleyalliance.org

All written questions and official responses will be distributed to all registered plan holders by addendum.

Question & Answers

QUESTION: Site access – the location of the rock construction entrance shown on the prints doesn’t seem to be best with the existing drop off. Is there a certain assumption you’d like us to make to ensure we are bidding “apples to apples” with other contractors?

RESPONSE: Site access will need to remain the same as in the drawings due to MVA Property Ownership.  We expect a bid to be consistent with what is being asked of the plans from all contractors.

 

QUESTION: Any additional clearing / grubbing that is known and we should assume in our proposal?

RESPONSE: Additional clearing or grubbing should be considered following the site walkthrough.

 

QUESTION: Are there recommendations for digging around the pipeline (i.e. soft dig, hydro)?
RESPONSE: The contractor shall coordinate with the gas company for any excavation near and around the gas line.  Peoples Natural Gas Company typically recommends the use of hydro excavation around gas lines to avoid any damage.  A representative from Peoples Natural Gas Company should be on site for excavation performed near the gas line.

 

QUESTION: Will the R7 rip rap require grouting the spacing?
RESPONSE: The grout that is used for Channel Section 1 shall be applied to the placement thickness of the R-7 riprap to fill the void area between the rock.  The grout shall be placed the entire width of the channel, including side slopes, and full depth between the voids of the R-7 riprap stone.

QUESTION: Are there permits that are still needed to be obtained for the project? Or would that be regarding bonding township roads.

RESPONSE: NPDES permit will be secured by MVA, any additional permits (i.e. bonding township roads) should be considered in your proposal.